Information on the 2023 Water Meter Replacement Project

Letter from Mayor Johnson Installation of new water meters

*We will be updating this website with the schedule for each phase of the water meter replacement project, so that resisdents  will know when meters will be replaced in their location. *

First Phase of the Meter Replacement Project:

Starting January 17th through January 31st the first phase of meter replacements, are listed below by street. We will update this list again in 2 weeks, with the next phase. 

VILLA ROSA RD

VILLA ROSA WAY

 VILLA ROSA LN

VILLA ROSA RDG

VILLA ROSA DR

VILLA ROSA TRL

VILLA ROSA PL

VILLA ROSA CT

VILLA COVE

BAR J RD

ETHERIDGE RD

SHELTON CR

REAGAN DR

CLINTON DR

DEAN CT

GARNER WAY

When will I know that my water meter has been installed and what should I expect?

**A door tag will be hung also once the meter is changed out, and that changes in water pressure during the installation process can result in temporary:

  • Discoloration of water
  • Air in the water lines, and
  • Small particles of sediment

Prior to using your water, we recommend that you flush your lines by turning on your bathtubs COLD water faucet for 3 to 5 minutes or use an outside faucet. Avoid flushing faucets that have aerator attachments or hot water faucets which could draw sediment into your water tank.

PLEASE NOTE: you DO NOT need to boil water because of this work.

More information about this project is available below in the "supporting documents" section: